House Construction Progress
Moving In
Moving In
Finished
Finished
Floors
Final Work
Lights
Deck Railing
Tile and Granite
Kitchen
Paint
Stairs
Porch/Closet
Interior Doors
Deck
Texturing
Irrigation
Drywall 3
Drywall 2
Drywall
Solar
Insulation
Exterior Paint
Ext. Paint 2
Stairs and Elec.
PG&E and Stairs
Installations
Siding
Roof + Siding
Roof + Siding
Roof
Windows
Roof 2
Roof 3
Roof 4
Constr.
Gable
Constr.
Trusses
Trusses 2
Trusses 3
9
8
7
6
5
4
3
2
Page 1
Grass Valley
Nevada City 1
Nev. City 2
Guestbook
5/16/08
The texturing with "imperfect" finish was done today.
A view of the back of the house.